Peru Poechos-Las Lomas-Quiroz 60kV transmission line project OPGW cable delivery

September 5, 2019

Latest company news about Peru Poechos-Las Lomas-Quiroz 60kV transmission line project OPGW cable delivery

On August 21, Dingli Power Equipment successfully completed the OPGW shipment of 82.36km

of the Peru Poechos-Las Lomas-Quiroz 60kV transmission line project. The delivery time of the

OPGW cable was 30 days. The project completed FAT inspection of the batch of 24 cores OPGW cable on August 10th.

latest company news about Peru Poechos-Las Lomas-Quiroz 60kV transmission line project OPGW cable delivery  0

 

The project is part of the overall supply of Peru Poechos-Las Lomas-Quiroz 60kV transmission line project.

Dingli has already completed the supply of more than 500 tons of angle steel towers in May.

 

latest company news about Peru Poechos-Las Lomas-Quiroz 60kV transmission line project OPGW cable delivery  1

 

Currently the corresponding hardware and fittings of the conductor and OPGW are also in orderly production.

 

latest company news about Peru Poechos-Las Lomas-Quiroz 60kV transmission line project OPGW cable delivery  2

 

latest company news about Peru Poechos-Las Lomas-Quiroz 60kV transmission line project OPGW cable delivery  3

 

latest company news about Peru Poechos-Las Lomas-Quiroz 60kV transmission line project OPGW cable delivery  4

 

latest company news about Peru Poechos-Las Lomas-Quiroz 60kV transmission line project OPGW cable delivery  5

Get in touch with us

Enter Your Message

julia@hndlpe.com
+8618037871307
86-18037871307
86-18037871307
86-18037871307